Build a house, addition, or fence
New construction, additions, and fences go through one permit at Public Works. Here is what the Building Law asks for, in order. For a private one-family house on public sewer, an unofficial tracker can follow the same path: start an application. The paper path is still valid. This site does not take fees.
Source research: . Older or unconfirmed requirements are marked below. Confirm current requirements with the agency.
You will end up with
- A DPW building permit, cleared by the agencies at the Business License and Permit Center
- Passed DPW inspections
- A certificate of occupancy before anyone moves in (new buildings and changes of use)
- 1
Confirm your lot, zoning, and boundaries
Department of Land Management, Division of Planning
- Know your lot, tract, block, and zoning district (the permit application asks for all four)
- The plot plan in step 2 must be drawn from an accurate boundary-line survey
- If what you want to build does not fit your zoning, you need a zone change or variance first
- Single-family setbacks: front 15 ft, rear 10 ft, side 8 ft. Minimum lot is 50 ft wide and 5,000 sq ft, or 10,000 sq ft in the rural A zone. Over the Northern Aquifer, Guam EPA sets lot size and setbacks (21 GCA §61501)
- Fences: a fence, wall, or hedge up to 6 ft high may go in any front, side, or rear yard (21 GCA §61503(f))
- 2
Prepare plans and a plot plan
You, your designer, or a licensed architect or engineer
- Plans: at least two copies of plans and specifications, drawn to scale, showing the work
- Plot plan: to scale, showing the new construction, every existing structure, distances from lot lines, and street grades
- DPW may ask for structural, mechanical, and electrical details. Engineering plans must be signed by the responsible engineer or architect
- For minor work, the building official may waive the plans or the plot plan
- 3
File the permit application
DPW Building Inspection and Permits Section, at the Business License and Permit Center
- Fill out the Application for Permit and Plan Review: check New Building, Add, or Fence Wall
- Give the cost of improvements, construction type, sewage (public or septic), water supply, and scope of work
- The owner or lessee signs, along with the contractor (with license number) and the architect or engineer (with seal number)
- In a flood zone, attach a topographic map and a flood elevation certificate
- Someone applying for the owner needs the owner's verified affidavit
- DPW contact: (671) 646-3104, BLPC@dpw.guam.gov
Not yet confirmed: how long review takes. The DPW director said some single-family permits take 5 to 7 working days (The Guam Daily Post), while contractors report waits of weeks to years (Isla Public, Oct 12, 2025). - 4
Pay the fee and start within 3 months
Paid to the Treasurer of Guam
- Fees follow Table 3-A of the Uniform Building Code, based on the total value of the work as set by DPW
- Homes pay half: a single-family house, fence, storage, or other residential improvement pays half the table fee
- The building official sets the valuation, and it includes roofing, electrical, plumbing, and air conditioning
- Fees double if work starts before the permit is issued (21 GCA §66408)
- The permit lapses if work does not start within 3 months, or stops for 3 months. Extensions must be in writing
Not yet confirmed: the law sets how fees are calculated, not a dollar amount, and we found no current dollar fee schedule online. Call DPW at (671) 646-3104 for the fee on your valuation. - 5
Pass inspections and get your certificate of occupancy
DPW building inspectors
- All permitted work is inspected during construction and must stay exposed until it is approved. The DPW Director sets the list of required inspections (21 GCA §66403)
- Schedule DPW inspections as work progresses, and keep the permit and approved plans on site
- No new building may be used until DPW issues a certificate of occupancy and it is posted on the premises
- Additions that change a building's use need a new certificate of occupancy too
- +
Clearing land or putting in a septic tank?
- Clearing, grading, and septic systems need Guam EPA review as well. See the clearing and grading route
- +
Becoming a licensed contractor?
Contractors License Board · 671-649-9676
- You need at least four years of experience in the last ten as a foreman, supervising employee, or contractor in the same field, and must be 18 or older. A company qualifies through its Responsible Management Employee
- File the Application for Examination with three certificates of experience, sworn statements from two people, a financial statement, and a project listing. The fee is $50 for each examination part, paid when you file
- The examination has two parts: the law as applied to construction, and your classification. You need 75% or higher on each. It is given on the 2nd and 4th Tuesday of the month
- After you pass, Revenue and Taxation, the Department of Labor, Land Management, and Public Works clear the license application. Public Health clears it only if you have alien labor, and the PEALS Board only for classification A
- The Board investigates and issues the license, or says in writing why not, within 45 working days after the application is filed. The first license fee is pro-rated by quarter, from $400 (July) down to $100 (April). The annual fee is due by June 30
Still unknown (help wanted)
- Typical total cost and real wait time for a house permit at the permit center today
- DPW's current inspection list for a typical home (foundation, framing, final)