Permit for work in a public road.

Unofficial tracker for the Public Works permit to dig in, build on, or place anything in a public road. The road is the whole right of way, not only the paved lanes. Water, sewer, and power hookups go through the utilities and are not tracked here.

6
steps on every file
1
more, only if a reviewer adds them
3
agencies that can be involved
$0
taken here. Fees are paid in person

Who touches it

Department of Public Works leads and sends the file to each agency that has to clear it.

gwagpadpwleads
Solid ring: on every file. Dashed ring: only when a reviewer routes it.

The steps

Open a stage to see what happens in it.

Intake1 step
  1. Intake at the Highways Divisiondpw · every file

    Filed with the Highway Encroachment and Permit section, (671) 649-3159. We found no application paper online.

Clearances3 steps
  1. Highways Division reviewdpw · every file

    What Public Works checks before it issues the permit is not published. This single review step stands in for it. Public Works may require a bond and may supervise the work at your cost (5 GCA §§53104, 53105(e)).

  2. Waterworks utility clearancegwa · every file

    Published: Waterworks needs the start date at least 3 full working days before work starts. Its clearance is valid for 10 days. Waterworks form ENGP-009

    For an excavation. Filed on Waterworks form ENGP-009 with the Public Works encroachment permit number and an aerial photo or engineering plans. Waterworks needs the start date at least 3 full working days before work starts, and its clearance is valid for 10 days.

  3. Power Authority utility clearancegpa · when routed

    The Power Authority publishes clearance guidelines for digging near its lines. We did not confirm its steps, so this stays off until a reviewer adds it. We found nothing for the phone company.

Fees2 steps
  1. Fee and deposit assessmentdpw · every file

    No dollar amount is stored. The law mentions an application fee and does not set an amount. An excavation also needs a deposit of $500 or 5% of the cost of the work affecting the road, whichever is more. A surety bond can stand in its place (5 GCA §53105(b)).

  2. Fee and deposit paid in persondpw · every file

    PermitGU does not take payment. A good repair gets the deposit back in full. The application fee is not refunded.

Issued1 step
  1. Permit issueddpw · every file

    The number shown is a demo number. After it is issued: tell the village mayor before digging starts and again when the road is restored (the next working day after an emergency dig), restore the road by the date on the permit, and fix a failed repair within 14 days. Public Works keeps the deposit for up to 3 months after the repair while it inspects. Paved repairs carry a 1-year warranty, unpaved 90 days (5 GCA §53105). This tracker stops at issue.

Good to know

  • This tracker does not replace the agency's own application. The applicant still files and signs the official one.
  • You upload 3 papers before you submit: Road deposit or performance bond, Schedule of work with the restoration deadline, Waterworks utility clearance request (ENGP-009).
  • The steps here were entered by a PermitGU admin from the public record. They are not confirmed by Department of Public Works.
  • Source: the official page this was built from.