Unofficial tracker
Conditional use permit.
Unofficial tracker for a conditional use permit: asking the Guam Land Use Commission to allow a use the zone permits only with its approval. The Commission reviews the site plan, including sewage disposal, access, parking, building location and size, and the effect on neighbors. Its conditions run with the land, and it can revoke the permit if they are not kept (21 GCA §61303).
- 9
- steps on every file
- 0
- more, only if a reviewer adds them
- 3
- agencies that can be involved
- $0
- taken here. Fees are paid in person
Who touches it
Department of Land Management leads and sends the file to each agency that has to clear it.
The steps
Open a stage to see what happens in it.
Intake1 step
- Intake at the Land Planning Divisiondlm · every file
Published: Land Management's process chart shows a preliminary application interview of about ten working days. Conditional use form, process chart
Filed in person, by appointment only, with the Commission's Executive Secretary at the Land Planning Division. The form cannot be mailed. The form asks for 32 sets of papers plus 9 electronic copies. Land Management's process chart shows a preliminary application interview of about ten working days and a case planner assigned. A copy goes to the village mayor (21 GCA §61106).
Clearances5 steps
- Notice sign posted on the lotdlm · every file
Set by law: the sign stays up with current information for at least 10 days in a row before each hearing or meeting. 21 GCA §61303(c)(1)
A sign at least 4 ft by 8 ft names the owner, developer, lot, proposed use, and each hearing date. It stays up with current information for at least 10 days in a row before each hearing or meeting (21 GCA §61303(c)). The application asks for a picture of the sign.
- Notice to owners within 500 feetdlm · every file
Set by law: written notice reaches owners within 500 feet at least 10 days before the hearing in person, or at least 25 days before by certified mail. 21 GCA §61303(c)(1)
Personal written notice at least 10 days before the hearing, or certified mail at least 25 days before (21 GCA §61303(c)). Missing a notice step makes any approval null and void. Land Management's chart also shows a newspaper notice 10 calendar days before. The applicant pays the mailing costs (21 GCA §61303(d)).
- Application Review Committee reviewarc · every file
Set by law: the review committee should send its reports within 30 days of filing, where possible. That is a target, not a hard limit. Land Management's process chart shows a 60 calendar day review period. 21 GCA §61106(b)
The committee should send its reports within 30 days of filing where possible (21 GCA §61106). Land Management's process chart shows a 60 calendar day agency review period instead. Which one applies in practice is not confirmed. No village hearing is held until the reports are in.
- Public hearing in the villagegluc · every file
Held in the affected village after the committee's reports reach the mayor (21 GCA §61106). Who runs the hearing and how it is scheduled is not confirmed.
- Commission decisiongluc · every file
The Commission approves, disapproves, or tables, then sends a Notice of Action. The law sets no deadline for this decision that we found. A project over $3,000,000 goes to a Hybrid Commission. In this tracker the review steps open together. The real order runs from the sign to the decision.
Fees2 steps
- Fee assessmentdlm · every file
No dollar amount is stored. The law sets a $50 filing fee for a conditional use permit (21 GCA §61660), plus the cost of mailed notice, paper, and envelopes (21 GCA §61303(d)). The form adds $2.00 for the first five pages and $0.25 for each page after. The real fee is due at filing. This tracker records it after review.
- Fee paid in persondlm · every file
PermitGU does not take payment.
Issued1 step
- Conditional use approved and recordeddlm · every file
The number shown is a demo number. The decision is filed with the Land Management Registrar and in Public Works records (21 GCA §61303). How to appeal a denial was not confirmed.
Good to know
- This tracker does not replace the agency's own application. The applicant still files and signs the official one.
- You upload 4 papers before you submit: Conditional use application (GLUC Form 01), Environmental impact assessment, Picture of the notice sign, Site plan and maps.
- The steps here were entered by a PermitGU admin from the public record. They are not confirmed by Department of Land Management.
- Source: the official page this was built from.