Repair typhoon damage
Roof torn, walls damaged, shutters gone. First find out whether your repair needs a permit at all. Small owner-done fixes often do not.
Source research: . Older or unconfirmed requirements are marked below. Confirm current requirements with the agency.
The short answer, from Guam's Building Law (21 GCA Chapter 66)
- Roof-covering exemption: the building owner, not a hired contractor, replaces 25% or less of the roof covering in a 12-month period
- Nonstructural repair exemption: the owner, lessee, employee, family, or friends (not a hired contractor) make repairs up to 25% of the building's value in 12 months, using the same materials and not affecting required fire resistance
- Confirm with DPW before work: you hire a contractor, the work affects structural integrity or required fire resistance, or it goes beyond those limits
- Rebuild to new-building code: if repairs in 12 months go over 50% of the building's value
- 1
Check which side of the line you are on
21 GCA §66104, Application to Existing Buildings
- Estimate the repair cost against the value of the building
- Replacing more than 25% of the roof covering means the new roof must meet the code for new buildings
- If repairs affect structural design or integrity, such as roof framing, beams, or load-bearing walls, confirm the permit and plan requirements with DPW before work starts. Do not assume owner-done work is exempt
Not yet confirmed: how DPW applies these exemptions to your particular damage, and whether any disaster-specific procedures apply. Confirm with DPW before starting work. - 2
Hire a licensed contractor
Contractors License Board · 671-649-9676
- Check the contractor on the board's published listing before you pay anything
- Check the suspended and revoked list too, which scam crews often end up on after big storms
- Make sure their license covers your kind of work, for example roofing or typhoon shutters
- 3
Apply for the building permit
DPW Building Inspection and Permits Section, at the Business License and Permit Center
- Fill out the Application for Permit and Plan Review and check "Repair" or "Reconstructed"
- Give the lot, tract, and block, the zoning district, the cost of improvements, and the scope of work
- The owner or lessee signs, along with your contractor (with license number) and any architect or engineer
- If the property is in a flood zone, attach a topographic map and a flood elevation certificate
- Roofing counts in the valuation that sets your permit fee, and fees double if work starts before the permit (21 GCA §66408)
- Someone applying for the owner must include the owner's verified affidavit authorizing them
- When plans are needed, bring one hard copy and five digital sets. For a renovation, give the scope of work and the total square footage
- The application routes to Public Works plan reviews and to other agencies (Land Management zoning, the Contractors License Board, the engineer and architect board, and others). The 2022 development guidebook says each applies "for what the project entails," so a small repair may need only some
Not yet confirmed: which reviews and clearances Public Works requires for a typical repair, and how long they take. We found no published processing time and no typhoon fast-track rule. - 4
Build to code and pass inspection
DPW building inspectors
- Schedule DPW inspections as work progresses
- Keep your permit and approved plans on site
- +
After a declared disaster
- Guam Homeland Security / Office of Civil Defense posts emergency updates, including any DPW permit changes and relief programs
- The only disaster permit exemption in the law is for government emergency utility and environmental work (21 GCA §66202.1(b)), not private homeowners
- After Typhoon Mawar, we found no executive order waiving permits for private repairs (EO 2023-02 did not)
- The free RISEUP temporary roof program after Mawar closed on June 30, 2023
Still unknown (help wanted)
- Permit fees for a typical roof repair, and how long a repair permit takes after a big storm
- Whether DPW fast-tracked typhoon repair permits in practice after Mawar