Work on a road, sidewalk, or driveway
Digging in, building on, or placing anything in a public road needs a written permit from Public Works. Water, sewer, and power hookups go through GWA and GPA. Here is what the law and the utilities ask for.
Source research: . Older or unconfirmed requirements are marked below. Confirm current requirements with the agency.
You will end up with
- A DPW permit for work in the road right of way
- A road restored to DPW standards, and your deposit back
- GWA water or sewer and GPA power connected to your lot
- 1
Check whether your work needs a DPW highway permit
Department of Public Works, Highways Division
- A "roadway" in the law is the entire width of the right of way, not just the paved lanes the public drives on (5 GCA §53101)
- You need a written DPW permit to: make an opening or excavation in a highway; place, change, or renew an encroachment (a pipe, pole, fence, sign, building, or other structure in, under, or over the highway); put an advertising sign in a highway; or plant, cut, or remove a tree or plant in a highway (5 GCA §53102)
- Doing any of these without a valid permit is a petty misdemeanor, and DPW may remove an unpermitted sign right away (§53102)
- DPW Highway Encroachment and Permit section: (671) 649-3159 or 649-3104. Rights-of-way: 649-3144 or 649-3146
Not yet confirmed: whether DPW has a separate driveway or curb cut permit form. We found no DPW permit form online. A new driveway apron is work in the right of way, so call the Highway Encroachment and Permit section at (671) 649-3159 before you cut a curb or pave to the road. - 2
Apply with a work schedule and a deposit
You or your contractor, at DPW Highways
- Every application to excavate a road needs a schedule of work with a deadline for restoring the road to its original condition or better (§53105(a))
- Deposit: on top of the application fee, an excavation needs a deposit of $500 or 5% of the cost of the work affecting the road, whichever is more. A performance bond from a surety licensed on Guam can stand in its place (§53105(b))
- DPW may also require a bond and may supervise the work, at your cost (§§53104, 53105(e))
- Utility clearance: before you dig, file Waterworks form ENGP-009 with your DPW encroachment permit number and an aerial photo or engineering plans, and stake or mark the area. Waterworks needs your start date at least 3 full working days ahead, and its clearance is valid for 10 days. The Power Authority publishes its own clearance guidelines for digging near its lines
- Permits can be revoked for cause on 30 days' written notice (§53103)
Not yet confirmed: the DPW permit application fee, the form, and how long approval takes. The law mentions an application fee but does not set an amount. Also, the online copy of Chapter 53 was last compiled in 2014, so later amendments may be missing. Confirm with DPW at (671) 649-3159. - 3
Do the work, tell the mayor, and restore the road
You or your contractor
- Tell your village mayor before digging starts, and again when the road is restored (§53105(f))
- Close the opening and restore the road by the date on your permit (§53105(a))
- DPW inspects the repair and keeps the deposit for up to 3 months after it is done. If the repair is not fixed within 14 days of DPW's notice, DPW can hire the work out and take the cost from your deposit or bond (§53105(b)(4))
- You warranty the repair for 1 year, or 90 days on an unpaved road. A good repair gets the deposit back in full; the application fee is not refunded (§53105(b)(4)(D))
- Emergencies: you may dig first only to prevent imminent danger or fix an unexpected service outage, then get the permit on the next working day. If DPW decides it was not an emergency, the penalty is $500 (§53105(d))
- 4
Connect water, sewer, and power
Guam Waterworks Authority (GWA) and Guam Power Authority (GPA)
- GWA water: apply at GWA Customer Service any time during construction, ideally before your contractor works in the right of way. Bring the customer information form, your certificate of title or deed of gift, your building permit, a map to the site, and an authorization if you are not the owner
- GWA gives you an account and work order number, then you fill out a Permit to Tap with the Permits and Inspections staff. Give GWA 48 hours' notice before trenching, meter installation, or tapping
- After inspection you get a Job Cost Sheet. Once paid, GWA says the meter is typically installed in 3 to 5 working days
- GWA sewer: the same steps, with a Wastewater Connection Permit and 48 hours' notice before trenching and connecting
- GWA Permits, Inspection and Enforcement: (671) 300-6058. Customer Service: (671) 647-7800
- GPA power: apply at the GPA payment center in Fadian, the Hagåtña satellite office, or GWA in upper Tumon, or by email. Bring the application, a photo ID, your deed, title, or lease with authorization, and a security deposit. The application fee is $25, and residential deposits run $125 to $500. GPA: (671) 647-5787
- New building? GPA asks you to apply 8 months before you need power (12 months for a pad-mounted transformer) so it can order materials. The plans need a load calculation and an engineer's seal, GPA engineering visits the site, and a DPW electrical inspection must pass before GPA sets the meter and energizes the service
- A place that already has a meter can be reconnected the same day for a $9 fee
Not yet confirmed: whether a utility line crossing a public road also needs a separate DPW highway permit when the property owner, not GWA or GPA, does the trenching. The law covers any opening in a highway, so ask DPW at (671) 649-3159. - +
Closing a road, or putting something on it?
- Placing a structure, pipe, pole, fence, or sign in, under, or over a road is an encroachment and needs a DPW permit (5 GCA §§53101, 53102)
- DPW can order an unpermitted encroachment removed (§§53106 to 53108)
Not yet confirmed: how to get a road or lane closed for work, and what traffic control plan DPW requires. We found no official rule or form online. Call DPW Highways (Traffic Management: (671) 646-3157, Highway Encroachment and Permit: 649-3159).
Still unknown (help wanted)
- DPW's current highway permit application form and fee
- DPW standards for driveway aprons, curb cuts, and sidewalk repair
- The process and lead time for a road or lane closure