Clear, grade, or install septic
Moving earth or putting in a septic tank brings in Guam EPA and Public Works, plus sign-offs from the utilities and land offices.
Source research: . Older or unconfirmed requirements are marked below. Confirm current requirements with the agency.
You will end up with
- A Guam EPA Clearing, Grubbing, Grading and Stockpiling permit
- A DPW clearing and grading permit, signed off by the agencies listed on it
- For septic: Guam EPA clearance on your building permit, and a passed water-tightness test
- A Fire Department burning permit, if you plan to burn cleared brush
- 1
Apply to Guam EPA
Guam EPA · 3304 Mariner Ave #17, Barrigada · 671-588-4751
- Guam EPA issues the Clearing, Grubbing, Grading and Stockpiling permit
- Apply online through the Guam EPA permit portal, or find the current form on the forms page
- Importing soil or fill? The forms page lists soil importation requirements too
Not yet confirmed: 2011 Guam EPA workshop slides describe this permit and a possible exemption for a one- or two-family house pad or driveway (2011 slides). Current fees and sign-off times are not published online. Ask Guam EPA. - 2
Get the DPW clearing and grading permit
DPW Division of Building Permits and Inspection
- The application asks for district, block, lot, tract, lot area, estimated cubic yards of cut and fill, soil description, start and finish dates, and contractor license number
- DPW routes it for approval by Land Management (zoning), Parks and Recreation, the Guam Power Authority, Guam EPA, the telephone authority, and the DLM Survey Division
- No burning on site unless the Fire Department has issued a burning permit
- Government agencies need this permit too, the same as private owners (21 GCA §66202.1)
The form posted online is an older version. Ask at the permit center whether a newer one is in use, and who handles the telephone sign-off now. Also not yet confirmed: delays often come from the Guam EPA, Agriculture, and Historic Preservation sign-offs, according to a March 2025 Public Auditor report (OPA 25-05). - 3
Building with a septic tank? Follow the 2024 rules
Guam EPA, under Public Law 37-105 (effective July 18, 2024)
- Septic tanks may no longer be built from hollow block (CMU)
- Concrete tanks must be pre-cast or poured monolithic, at least 4000 psi at 28 days
- Inlet and outlet must be at least 6 feet apart, with the inlet at least 3 inches above the outlet
- Every tank must pass a water-tightness test that Guam EPA observes: fill, hold 24 hours, refill, and hold for 1 hour
- No occupancy permit is issued until the tank passes
- 4
Burning cleared brush?
Guam Fire Department
- Get a burning permit before burning anything on site
Still unknown (help wanted)
- Permit fees for a typical residential lot clearing
- Whether you need both the EPA and DPW permits for a small residential lot, or the two have been combined
- How long sign-offs take from all six agencies